Ducks overlooking outside scenery on bridge.

Sharp v Blank and others [2017] EWHC 3390 (Ch)

07 March 2018.

The Court considered the Defendants' application for approval of their revised cost budget on the basis that there had been significant developments in the litigation.

The judgment provides helpful clarification of the Court's jurisdiction to approve costs that have already been incurred between the date of the original approved budget and the date of the application hearing. The judgment is useful for practitioners in its examination of the circumstances which can be said to represent 'significant developments' in a case. 

Civil Procedure Rules

The relevant cost budgeting provisions of the Civil Procedure Rules (the CPR) can be found in CPR 3.12 to 3.18 and in Practice Direction 3E.  Of particular significance in this case are paragraphs 7.4 and 7.6 of Practice Direction 3E. The guidance in PD 3E 7.4 states that:

"As part of the cost management process the court may not approve costs incurred before the date of any costs management hearing.  The court may, however, record its comments on those costs and will take those costs into account when considering the reasonableness and proportionality of all subsequent budgeted costs". 

The guidance in PD3E 7.6 stipulates that:

"Each party shall revise its budget in respect of future costs upwards or downwards, if significant developments in the litigation warrant such revisions […] The court may approve, vary or disprove the revisions having regard to any significant developments which have occurred since the date when the previous budget was approved or agreed".  

 Background

The underlying litigation is brought by approximately 5,800 claimants who make serious allegations against five former directors of Lloyds TSB Group and Lloyds itself in relation to the acquisition by Lloyds of Halifax Bank of Scotland plc and its participation in the government's Recapitalisation Scheme in 2008 and 2009.

A costs management order was made in January 2017 (at the request of the Claimants) to ensure that the Claimants were aware of the extent of their costs exposure.  The Claimants approved cost budget stood at approximately £17 million, whilst the Defendants' totalled approximately £19 million.

Points of principle

On 19 October 2017 the Defendants issued an application to revise their cost budget.  They raised seven significant developments that they say required them to revise their budget pursuant to paragraph 7.6 of PD3E. The Claimants opposed the Defendants' application on three main points of principle:

  1. Jurisdiction: It was said that (a) the Court had no jurisdiction to deal with any costs that were already incurred by the Defendants prior to the date of the application hearing; (b) the Court had no power, in any event, to treat interim applications as being significant developments; and (c) none of the seven reasons identified by the Defendants were significant developments that warranted revision of the cost budget.
  2.  Lateness: The hearing of the application took place during the trial and the application was issued shortly after trial commenced.As such, it was argued that the application was made too late and the Court should therefore not entertain it.
  3. Oppression: It was said that the application was intended to be oppressive to the Claimants given their precarious funding position

Decision

The Master granted the Defendants' application in part as follows.

Jurisdiction

Costs already incurred

The Court had jurisdiction under CPR PD 3E 7.6 to approve a revised costs budget where the revisions related to costs which had been incurred between the date of the budget and the date of the hearing. 

The Master acknowledge that although, if read literally, PD3E 7.4 prohibited the Court from approving costs incurred before the date of any costs management hearing, the requirements of this paragraph were "impossible to implement".  By way of example, the Master noted that CPR 3.13(1) requires parties to file and exchange costs budgets 21 days prior to the first CMC.  In each case the budget will be at least three weeks out of date and the estimated costs for the CMC itself will have been incurred by the time the hearing of the CMC has concluded.

The Master noted that the language of PD3E 7.6 "points towards taking the previous budget as a base reference point", and confirmed that costs incurred since the date of the last approved budget which related to significant developments were, for the purposes of the revision, estimated costs.

Interim applications treated as significant developments

The Court found that interim applications may be significant developments, as may the consequences that flow from any interim application.   Such applications could therefore form the basis of a revision to a party's cost budget under PD 3E 7.6.

Significance must be understood in light of the size, complexity and manner in which the litigation unfolded.  It may also take into account the likely additional expense that has been, or is expected to be, incurred.   Certain applications might, in themselves, not be significant developments, but may lead to work that can be characterised as significant.  As such, the Court should look at the totality of related developments.

Significant developments

With regard the seven significant developments noted by the Defendants, the Master permitted adjustments to the Defendants' cost budget in relation to items 1 to 4 below, but not to items 5 to 7.

  1. Extension to the trial timetable: Whilst the mere fact that there was a longer trial timetable was not of itself a sufficient basis upon which to increase the budget, the scale and complexity of the claim meant that preparations for and conducting the trial were "a vast enterprise".The Judge noted that if necessary, the extension to the trial timetable "could be broken down into a series of significant developments".
  2. Defendants' application for specific disclosure: The provision of 984 additional documents by the Claimants was found to be a significant development.The Master commented that "[…] reviewing nearly 1,000 documents is a major task" and was satisfied that the Defendants' cost budget should be increased.
  3. Claimants' additional expert evidence: Service of the Claimants' additional expert report was a significant development as it was a change from the agreed basis upon which expert evidence was provided. It could not have been predicted by the Defendants and it was necessary for the Defendant's expert to respond to it.
  4. Defendants' additional expert evidence: The service of the Claimants' expert evidence was a significant development (as per issue three above), and the Defendants' additional expert evidence was a cost that flowed from this.
  5. Claimants' third party disclosure application: The application was held to be part of the Claimants' task of trial preparation and as such did not lead to work that could properly be characterised as a significant development.
  6. Questions put to the Defendants' experts: The Court held that the fact that the scope of the questions put to its experts by the Claimants went beyond what could reasonably have been foreseen was not a significant development, and commented that "There must be something more than merely a modest increase in the anticipated cost of the work to amount to a significant development".
  7. Response from the Claimants' expert: The Defendants put a number of questions to one of the Claimants' experts which resulted in a lengthy response.The Master held that a modest adjustment to the Claimants' case arising in the course of the exchange and consideration of expert evidence could not be properly characterised as significant.

Lateness

The Master commented that it was "deeply unattractive for the claimants to complain that the application [had] been made late" in circumstances where the Defendants first raised the need to revise budgets on 21 July 2017 and no response was provided by the Claimants until 22 September 2017.  The Court found the Defendants to have taken reasonable steps to ensure that their application was made in a timely fashion and was brought on for the hearing as soon as practicable.

Oppression

The Master did not accept the Claimants' complaint that the application had been made to divert their attention away from the trial and had been presented in a "heavy-handed and document-heavy way".   The judgment confirmed that pursuant to PD3E 7.6, the revision of costs budgets is not optional, but rather is a requirement.  If there were significant developments in a case and the parties asked the Court to revise cost budgets, it would be very unusual for the Court simply to refuse to make any order at all. 

Comment

The judgment provides useful commentary for practitioners on the Court's jurisdiction to approve costs that have already been incurred between the date of the original budget and the date of the application.  A party's ability to apply for retrospective amendments is a contentious topic and the pragmatic approach taken by the Master in accepting that "some degree of retrospectivity is inevitable if the costs management regime is to work" will provide comfort for litigants. 

The Court's confirmation that interim applications (and the consequences that flow from them) can equate to significant developments clarifies the juxtaposition of PD3E 7.6 and 7.9 (which expressly provides that interim applications are to be treated as additional to the approved budgets).  The judgment explains that the two provisions are not mutually exclusive but should be read together and construed as a whole.  Whilst obviously case specific, the examination of the circumstances which were held to be 'significant developments' provides useful guidance for practitioners dealing with revisions to costs budgets.